QUESTION 101

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

 

A.

Arrow Diagramming Method (ADM)

B.

Precedence Diagramming Method (PDM)

C.

Critical Path Method (CPM)

D.

Critical Chain Method (CCM)

 

Correct Answer: B

 

 

QUESTION 102

Which of the following is the BEST way to manage stakeholder expectations?

 

A.

Provide the stakeholder with a copy of the project charter.

B.

Approve stakeholder requests.

C.

Obtain stakeholder buy-in.

D.

Have the stakeholders complete a change request form.

 

Correct Answer: C

 

 

QUESTION 103

Refer to the attached Exhibit. Which of the following is the duration of the critical path in the diagram?

 

clip_image002

 

A.

2

B.

5

C.

6

D.

7

 

Correct Answer: D

 

 

QUESTION 104

A project change is approved by the Change Control Board that modifies the project scope. Which of the following is the NEXT step that the project manager should take?

 

A.

Construct a detailed plan to implement the change.

B.

Analyze the impact of the change request.

C.

Document the request in the change control log.

D.

Request a meeting with the project sponsor to discuss scope creep.

 

Correct Answer: A

 

 

QUESTION 105

Which of the following is true of a work breakdown structure (WBS)? (Select Two).

 

A.

It consists of work packages at the top level which are decomposed to increasingly detailed levels.

B.

It is a quantitative analysis tool used in quality management to analyze defects.

C.

Each descending level represents an increasing detailed definition of the project work.

D.

It is developed during the planning process and used to create the project scope statement.

E.

It organizes and defines the total scope of the project.

 

Correct Answer: CE

 

 

 

 

 

QUESTION 106

Which of the following skills would be the MOST useful in assembling an effective project team in a functional organization?

 

A.

Compromising

B.

Negotiation

C.

Estimating

D.

Padding

 

Correct Answer: B

 

 

QUESTION 107

A project manager is comparing their budgeting techniques to the most successful project in the
companys history. Which of the following techniques is being utilized?

 

A.

Benchmarking

B.

Return on investment

C.

Process analysis

D.

Cost-benefit analysis

 

Correct Answer: A

 

 

QUESTION 108

A network diagram shows two critical paths for a project. Which of the following will MOST likely increase?

 

A.

Staff

B.

Risk

C.

Cost

D.

Time

 

Correct Answer: B

 

 

QUESTION 109

A project manager receives a request for a minor change to one of the deliverables. Which of the following documents would MOST likely be impacted?

 

A.

Work Breakdown Structure (WBS)

B.

Project charter

C.

Communication plan

D.

Quality plan

 

Correct Answer: A

 

 

QUESTION 110

A Pareto chart is a special type of:

 

A.

histogram.

B.

Ishikawa diagram.

C.

scatter diagram.

D.

run chart.

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in JK0-017 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.