[Free] Download New Updated (December) CompTIA JK0-017 Exam Questions 241-250

Ensurepass

QUESTION 241

Which of the following will have the GREATEST impact upon the outcome of a project? (Select Two).

 

A.

Quality metrics

B.

Scope creep

C.

Performance reports

D.

Project life cycle

E.

Project delays

 

Correct Answer: BE

 

 

 

 

 

 

 

 

QUESTION 242

Two SMEs disagree with the designed plan for a particular component. The project will be delayed if the plan is not approved today. The project manager demands the SMEs work together to incorporate their modifications by the close of business today. Which of the following resolution techniques was used?

 

A.

Negotiating

B.

Forcing

C.

Smoothing

D.

Compromise

 

Correct Answer: B

 

 

QUESTION 243

During a status meeting, a team member informs the project manager of a possible risk. Which of the following is the FIRST action the project manager should take?

 

A.

Record the risk in the risk register.

B.

Work with the team to develop a risk response.

C.

Perform an initial prioritization of the risk.

D.

Determine the probability and impact of the risk.

 

Correct Answer: A

 

 

QUESTION 244

A quality control technician is diagramming test results on a run chart. The chart consists of twenty-five points, with twelve consecutive points below the median line; however, the other thirteen points alternate above and below the median line. The twelve consecutive points represent which of the following?

 

A.

The run denotes common cause variation.

B.

The quality process is flawed and should be completed again.

C.

The product does not adhere to specification.

D.

The run denotes special cause variation.

 

Correct Answer: D

 

 

QUESTION 245

When a project ends unexpectedly, which of the following should the project manager do?

 

A.

Create an end document to add to the file before moving on to another project.

B.

Create a document identifying the negative impact of the early project ending to give to the customers management.

C.

Perform project close out with full documentation and review.

D.

Perform a limited project close that consists of releasing team members.

 

Correct Answer: C

 

 

 

QUESTION 246

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

 

A.

-$1,000

B.

$1,000

C.

-$3,000

D.

$3,000

E.

There would be a 25 percent cost decrease.

F.

There would be a 75 percent cost increase.

G.

The project is over-budget.

H.

The project is under-budget.

 

Correct Answer: A

 

 

QUESTION 247

Whose approval should be obtained before modifying the scope of a project?

 

A.

Project team

B.

Executive management team

C.

Change control board

D.

Stakeholders

 

Correct Answer: C

 

 

QUESTION 248

Which of the following would require that the project risk register be updated?

 

A.

A qualitative risk analysis is performed

B.

A stakeholder has concerns about material delays

C.

The risk management plan is created

D.

Increased costs for required materials

 

Correct Answer: A

 

 

QUESTION 249

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?

 

A.

Bottom-up estimating

B.

Rolling wave planning

C.

Resource leveling

D.

Fast tracking

 

Correct Answer: D

 

 

 

 

 

QUESTION 250

A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time. Which of the following will be impacted?

 

A.

Project scope will be impacted.

B.

Quality will be impacted.

C.

WBS will be impacted.

D.

SOW will be impacted.

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in JK0-017 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.