QUESTION 251

If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?

 

A.

.50

B.

.75

C.

1.25

D.

1.75

 

Correct Answer: B

 

 

QUESTION 252

At a project milestone meeting, the project sponsor asked about a deliverable that is not on the project plan. Which of the following should the project man
ager do to compensate for this unmet expectation?

 

A.

Review the scope with the vendor.

B.

Review the scope with the customer.

C.

Review the scope with the team.

D.

Review the scope with the sponsor.

 

Correct Answer: D

 

 

QUESTION 253

Monitoring and controlling project work is a control process function that spans from:

 

A.

the creation of the project work plan to the completion of the work breakdown structure (WBS).

B.

project kickoff to the project completion, including documentation of lessons learned.

C.

project kickoff to the project plan generation.

D.

the creation of the project work plan to the completion of the statement of work (SOW)

 

Correct Answer: B

 

 

QUESTION 254

In order to meet governmental requirement Q555, all materials must meet spec #A-223 qualifications. This is an example of which of the following types of dependencies? (Select Two).

 

A.

Internal

B.

Discretionary

C.

Fixed

D.

External

E.

Mandatory

 

Correct Answer: DE

 

 

QUESTION 255

Two team members refuse to work together and have undermined the project with their constant bickering. The project manager needs both of them to complete the project. The team members meet and agree to work at different times. Which of the following conflict resolution styles is being used?

 

A.

Forcing

B.

Smoothing

C.

Confronting

D.

Compromising

 

Correct Answer: D

 

 

QUESTION 256

Which of the following is the purpose of a milestone schedule?

 

A.

A detailed summary of the project milestones that need to be achieved.

B.

A summary level timetable of the major project milestones.

C.

A summary of the anticipated milestones and the issues identified for the project.

D.

A detailed summary of the anticipated milestones and risks identified for the project.

 

Correct Answer: B

 

 

QUESTION 257

An ongoing project has a BAC of $450,000, an EV of $110,000 and an AC of $100,000. Which of the following is the CPI of the project?

 

A.

$340,000

B.

1.1

C.

$10,000

D.

.91

 

Correct Answer: B

 

 

QUESTION 258

Faced with a complex project with many stages, which of the following is the BEST action for the project manager to take?

 

A.

Employ phase closure meetings.

B.

Encourage vendors to work overtime.

C.

Request a schedule extension.

D.

Hire additional contractors.

Correct Answer: A

 

 

QUESTION 259

Which of the following is the BEST point for a project manager to join a project?

 

A.

Project initiation

B.

Project pre-planning

C.

Project planning

D.

Project executing

 

Correct Answer: B

 

 

QUESTION 260

A project manager has analyzed work performance information and identified alarming variances in the project deliverable. Which of the following would be the BEST response for the project manager?

 

A.

Perform a qualitative risk assessment.

B.

Speak with the project sponsor about possible solutions.

C.

Approve a change request to correct the actions.

D.

Recommend corrective actions.

 

Correct Answer: D

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in JK0-017 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.