QUESTION 271

A project team is estimating the amount of time needed to perform an activity. They have recommended an optimistic, pessimistic, and most likely duration to complete the activity. Which of the following would be the BEST tool to estimate the final duration?

 

A.

PERT

B.

GANTT

C.

GERT

D.

WBS

Correct Answer: A

 

 

QUESTION 272

Which of the following is an important aspect of formal project closure?

 

A.

Assign resources to the next project.

B.

Analyze quality and ensure standards are being met.

C.

Document lessons learned for use in future projects.

D.

Modify the WBS to include all the change requests that occurred during the project.

 

Correct Answer: C

 

 

QUESTION 273

Which of the following is a component of a project charter?

 

A.

Responsibility assignment matrix

B.

Risk register

C.

Work Breakdown Structure (WBS)

D.

Problem statement

 

Correct Answer: D

 

 

QUESTION 274

Which of the following are schedule compression techniques? (Select Two).

 

A.

Fast tracking

B.

Critical Path Method (CPM)

C.

Crashing

D.

PERT analysis

E.

Schedule network analysis

 

Correct Answer: AC

 

 

QUESTION 275

Which of the following would be the impact upon a project if the CPI for the project is .75?

 

A.

The project is under-budget.

B.

There would be a 25 percent cost decrease.

C.

There would be a 75 percent cost increase.

D.

The project is over-budget.

 

Correct Answer: D

 

 

QUESTION 276

Which of the following would be contained in the problem statement within the project charter?

 

A.

The issues that might block a vendor’s success.

B.

The conflict between management and the project vendors.

C.

The issues the customer wants resolved.

D.

The conflict management style that will be used during the project.

 

Correct Answer: C

 

 

QUESTION 277

Which of the following describes a quality control tool used to analyze defects based upon number of occurrences?

 

A.

Pareto diagram

B.

Scatter diagram

C.

Fishbone diagram

D.

Ishikawa diagram

 

Correct Answer: A

 

 

QUESTION 278

Which of the following documents would MOST likely be updated to reflect an approved time change for a regularly scheduled weekly status meeting?

 

A.

Work Breakdown Structure (WBS)

B.

Responsibility assignment matrix

C.

Communication plan

D.

Change request

 

Correct Answer: C

 

 

QUESTION 279

Which of the following should be included in a Gantt chart to analyze a project schedule? (Select Three).

 

A.

Risks

B.

Probability

C.

Cost analysis

D.

Start date

E.

Activity durations

F.

Finish date

 

Correct Answer: DEF

 

 

QUESTION 280

Which of the following are characteristics of an approved project charter? (Select Two).

 

A.

Provides the prioritization of work from the stakeholders.

B.

Defines the project managers authority.

C.

Identifies what the project manager wants to derive from the project.

D.

Increases the number of just-in-time processes required to decrease scope creep.

E.

Validates the existence of a project.

 

Correct Answer: BE

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , , , . Bookmark the permalink.