Ensurepass

QUESTION 31

Which of the following is the BEST communication option for team building?

 

A.

Send an email transmission to introduce the project.

B.

Send a completed project charter to introduce the project.

C.

Leave a voicemail message to introduce the project.

D.

Schedule a face-to-face meeting to introduce the project.

 

Correct Answer: D

 

 

QUESTION 32

A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur?

 

A.

Qualitative risk analysis

B.

Quantitative risk analysis

C.

Risk response planning

D.

Risk identification

 

Correct Answer: A

 

 

QUESTION 33

A project manager is informed that material expenditures will increase. Which of the following documents should be referenced to address this increase?

 

A.

Work Breakdown Structure (WBS)

B.

Cost management plan

C.

Approved project charter

D.

Project scope document

 

Correct Answer: B

 

 

QUESTION 34

A project manager has decided to increase the number of resources working on critical path activities. This is an example of:

 

A.

rolling wave planning.

B.

resource leveling.

C.

fast tracking.

D.

crashing.

 

Correct Answer: D

 

 

QUESTION 35

Which of the following elements would be needed to prepare an effective project scope document?

 

A.

An approved project milestone schedule

B.

An approved risk assessment document

C.

An approved project charter

D.

A responsibility assignment matrix

 

Correct Answer: C

 

 

QUESTION 36

Which of the following is the purpose of a Pareto diagram?

 

A.

To show the sequence in which work will be performed

B.

To create the process that will complete the project

C.

To determine the critical path

D.

To direct team efforts to the areas that will have the most impact

 

Correct Answer: D

 

 

QUESTION 37

A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?

 

A.

Distribute details of the change per the communication plan, and implement according to the change control process.

B.

Ask the change control board to schedule the change, and when scheduled, identify the individual team member responsible for implementing it.

C.

Email the project team, identifying the team member responsible for implementing the change, and then schedule it with the appropriate team members.

D.

Identify the team member responsible for implementing the change and direct the team member to inform the rest of the project team of the date and time of implementation.

 

Correct Answer: A

 

 

QUESTION 38

Which of the following would be a direct output of the initiating process group? (Select Two).

 

A.

Project charter

B.

Project management plan

C.

Statement of Work (SOW)

D.

Work Breakdown Structure (WBS)

E.

Preliminary scope statement

 

Correct Answer: AE

 

 

QUESTION 39

Which of the following are process groups in the project life cycle? (Select Three).

 

A.

Accepting

B.

Mitigating

C.

Avoiding

D.

Initiating

E.

Closing

F.

Planning

 

Correct Answer: DEF

 

 

QUESTION 40

Project information is received by the project manager in a number of different formats from team members. Which of the following would be the BEST way for the project manager to standardize the information?

 

A.

Create project templates.

B.

Require supervisor approval of documentation.

C.

Use document version control.

D.

Implement organizational format standards.

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , , , . Bookmark the permalink.