QUESTION 41

Which of the following tools would be used to determine the relationship between two changed variables?

 

A.

Scatter diagram

B.

Qualitative risk analysis

C.

Ishikawa diagram

D.

Monte Carlo analysis

 

Correct Answer: A

 

 

QUESTION 42

Two members of a team have had difficulty working together in the past. Which of the following sho
uld the project manager do to facilitate communication between the team members?

 

A.

Discuss the problem at the next project meeting and have the team members find a solution.

B.

Evaluate both members and replace the least important member.

C.

Speak with both team members and address concerns.

D.

Dismiss both team members and replace them with new members.

 

Correct Answer: C

 

 

QUESTION 43

Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).

 

A.

The project manager should consult the project sponsor and customer to review the current quality requirements.

B.

The project manager should request a peer review of the project to determine if it meets the customers quality standards.

C.

The project manager should change the scope of the project to meet the customers expectations of quality standards.

D.

The project manager should check the finished product to determine if it meets the customers quality standards.

E.

The project manager should outsource to obtain the best resources for the project.

 

Correct Answer: BD

 

 

QUESTION 44

Which of the following components are included in a communication plan? (Select Two).

 

A.

Statement of Work (SOW)

B.

Risk matrix

C.

Frequency

D.

Work Breakdown Structure (WBS)

E.

Distribution list

 

Correct Answer: CE

 

 

QUESTION 45

Transition plans include which of the following elements?

 

A.

Work Breakdown Structure (WBS)

B.

Project warranty

C.

Project process reports

D.

Earned value calculations

 

Correct Answer: B

 

 

QUESTION 46

In which of the following organization types would a project manager have the LEAST amount of project authority?

 

A.

Functional

B.

Strong Matrix

C.

Balanced Matrix

D.

Weak Matrix

 

Correct Answer: A

 

 

QUESTION 47

The project manager crashes a project that is behind schedule and under-budget. Which of the following will be the intended result?

 

A.

The project will be behind schedule and over-budget.

B.

The project will be on schedule but over-budget.

C.

The project will be on schedule and on-budget.

D.

The project will be behind schedule and on-budget.

 

Correct Answer: C

 

QUESTION 48

Refer to the attached Exhibit. Which of the following is the float of path Start-C-E-Finish in the network diagram?

 

clip_image002

 

A.

Zero

B.

One

C.

Three

D.

Five

 

Correct Answer: A

 

 

QUESTION 49

Which of the following is included in the project charter?

 

A.

A work performance report

B.

A cost assessment

C.

A high level plan

D.

A risk assessment

 

Correct Answer: C

 

 

QUESTION 50

Which of the following represents the appropriate order of an effective change management process?

 

A.

Identify change, perform impact analysis, approve or deny change, update applicable project plan components, document change.

B.

Identify change, document change, perform impact analysis, approve or deny change, update applicable project plan components.

C.

Identify change, document change, perform impact analysis, update applicable project plan components, approve or deny change.

D.

Identify change, document change, approve or deny change, perform impact analysis, update applicable project plan components.

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in JK0-017 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.