QUESTION 51

Two of the stakeholders cannot agree on the project timeline or budget. The project is critical to the success of the company. Which of the following actions should the project manager take NEXT?

 

A.

Invite all of the stakeholders to a meeting to discuss project requirements.

B.

Document the points of agreement and create the timeline and budget based upon the expectations of the majority of the stakeholders.

C.

Modify the project scope to bring it into alignment with the stakeholders expectations.

D.

Inform the stakeholders that the project will be cancelled if they cannot agree.

 

Correct Answer: A

 

 

QUESTION 52

Which of the following is a use for a Pareto diagram?

 

A.

In procurement management to evaluate vendor proposals.

B.

In cost management to determine actual versus expected project costs.

C.

In quality management to identify and prioritize problem areas.

D.

In risk management to assess potential project risk occurrences.

 

Correct Answer: C

 

 

QUESTION 53

Which of the following shows a project that is presently over its financial budget?

 

A.

CPI = 1.4

B.

CPI = 0

C.

CV = +$11,000

D.

CPI = 0.8

 

Correct Answer: D

 

 

QUESTION 54

Which of the following is true of fast tracking a schedule?

 

A.

Project schedule critical path will change.

B.

Project activities will be performed concurrently.

C.

Project schedule is shortened by decreasing the project scope.

D.

Project schedule lead times are increased.

 

Correct Answer: B

 

 

QUESTION 55

A project manager is performing activity duration estimation. This project will have conditional decisions. Which of the following tools would be the BEST to use?

 

A.

GERT

B.

Gantt chart

C.

PERT

D.

EVM

 

Correct Answer: A

 

 

QUESTION 56

Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select Three).

 

A.

Time zones

B.

Travel costs

C.

Co-location of resources

D.

The project plan

E.

Scheduled vacations

F.

Language barriers

 

Correct Answer: ABF

 

 

QUESTION 57

A SPI of 1.1 means that the project is:

 

A.

under-budget.

B.

behind schedule.

C.

ahead of schedule.

D.

over-budget.

 

Correct Answer: C

 

 

QUESTION 58

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?

 

A.

Update the p
roject plan to accommodate the changes.

B.

Perform an impact analysis.

C.

Organize a stakeholder meeting to review the changes.

D.

Change the project scope to reflect the change request.

 

Correct Answer: B

 

 

QUESTION 59

Which of the following techniques can a project manager use to assist with quality planning? (Select Three).

 

A.

Peer review

B.

Critical Chain Method (CCM)

C.

Inspection

D.

Performance Evaluation and Review Technique (PERT)

E.

Work Breakdown Structure (WBS)

F.

Benchmarking

 

Correct Answer: ACF

 

 

QUESTION 60

A project team member is uncertain how many activities are required to complete a task. Which of the following documents should be referenced?

 

A.

Key Performance Indicators (KPIs)

B.

Project charter

C.

Work Breakdown Structure (WBS)

D.

Statement of Work (SOW)

 

Correct Answer: C

 

Free VCE & PDF File for CompTIA JK0-017 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in JK0-017 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.