[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 151-160

Ensurepass

QUESTION 151

Two SMEs disagree with the designed plan for a particular component. The project will be

delayed if the plan is not approved today. The project manager demands the SMEs work together

to incorporate their modifications by the close of business today. Which of the following

resolution techniques was used?

 

A.     Negotiating

B.     Forcing

C.     Smoothing

D.     Compromise

 

Correct Answer: B

 

 

QUESTION 152

A project manager has been informed that a project deliverable must be completed by

September 1st. Which of the following BEST describes this situation?

 

A.     Project assumption

B.     Project constraint

C.     Project risk

D.     Acceptance criteria

 

Correct Answer: B

 

 

QUESTION 153

Which of the following are characteristics of a project? (Select TWO).

 

A.     Temporary

B.     Ongoing

C.     Unique

D.     Repetitious

E.      Contains multiple objectives

 

Correct Answer: AC

 

 

QUESTION 154

Which of the following statements BEST describes the project sponsor?

 

A.     They actively participate during the project.

B.     They have an active interest in the project’s outcome.

C.     They have an impact on the process.

D.     They attend the weekly team meetings.

 

Correct Answer: B

 

 

QUESTION 155

When performing risk analyses, which of the following areas are the MOST closely examined?

(Select TWO).

 

A.     Environment

B.     Schedule

C.     Cost

D.     Leadership

E.      Quality

 

Correct Answer: BC

 

 

QUESTION 156

During the execution stage, the project manager learns that a team member has resigned from

the company. The project manager determines that there are no existing qualified team

members available to fill the vacancy. Which of the following should the project manager do

FIRST?

 

A.     Review the staffing plan.

B.     Outsource the position.

C.     Delay the scheduled delivery date.

D.     Remove the tasks from the WBS.

 

Correct Answer: A

 

 

QUESTION 157

A project manager is finding that stakeholders are not up-to-date on the project status. When

determining how to correct the problem, the project manager should FIRST review which of the

following documents?

 

A.     Responsibility matrix

B.     Statement of Work (SOW)

C.     Issue log

D.     Communications plan

 

Correct Answer: D

 

QUESTION 158

The project manager should officially release team members:

 

A.     when the resource manager requests return

B.     during project closure process

C.     as soon as the resource’s assigned tasks are complete

D.     at the end of the executing phase

 

Correct Answer: B

 

 

QUESTION 159

Midway during a project, the sponsor tells the project manager to cancel the project. The project

manager should:

 

A.     call the project manager’s manager and request an immediate transfer to a new contract

B.     confirm with the customer that the project should be stopped

C.     send a sponsor change request to the change control board

D.     begin a full contract closure process

 

Correct Answer: D

 

 

QUESTION 160

A large increase in the price of a critical component threatens to increase the project costs

significantly and the current vendor will not renegotiate. Which of the following should the

project manager do NEXT?

 

A.     Provide a change order to the customer.

B.     Continue the project according to the schedule.

C.     Return to the qualified sellers list.

D.     Ask the project sponsor for more money.

 

Correct Answer: C

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.