QUESTION 161
There is a high probability of a needed resource becoming unavailable. The project manager
determines the impact to be low; therefore, the MOST likely response to the identified risk is to:
A. accept it
B. avoid it
C. minimize it
D. mitigate it
Correct Answer: A
QUESTION 162
It is important to check the project scope with all stakeholders because it:
A. creates a professional working environment
B. is easier to get invoices processed
C. helps the team members get along better
D. facilitates acceptance from all people affected
Correct Answer: D
QUESTION 163
An organization can initiate a project charter by:
A. approving change requests
B. defining the business requirements
C. tracking team member performance
D. identifying the risk response plans
Correct Answer: B
QUESTION 164
To validate a project, it would be important to:
A. identify the key stakeholders
B. analyze the CPI
C. define the quality metrics
D. recommend corrective actions
Correct Answer: A
QUESTION 165
A project scope document should include which of the following items? (Select TWO).
A. Cost control
B. Continuous service improvements
C. Key performance indicators
D. Detailed objectives
E. Risk management plan
Correct Answer: CD
QUESTION 166
Which of the following tools can be used to estimate the number of resources required to
complete a project? (Select TWO).
A. Project management software
B. Expert judgment
C. Monte Carlo analysis
D. Risk assessment
E. Quality checklist
Correct Answer: AB
QUESTION 167
A stakeholder asks a project manager to cut costs by lowering the quality of the finished product.
Which of the following should the project manager do NEXT?
A. Communicate the change to the project resources.
B. Ask the stakeholder to submit a change request.
C. Revise the project scope statement.
D. Crash the schedule.
Correct Answer: B
QUESTION 168
Which of the following may have a significant adverse impact upon the successful completion of
an international project? (Select THREE).
A. Time zones
B. Travel costs
C. Co-location of resources
D. The project plan
E. Scheduled vacations
F. Language barriers
Correct Answer: ABF
QUESTION 169
During the initial project planning process, which of the following is MOST important to consider
when completing a project for a regulated entity?
A. The influence of standards compliance.
B. The influence of skilled resources.
C. The influence of the task assignments.
D. The influence of project peer review regulations.
Correct Answer: A
QUESTION 170
The stakeholders have asked for numerous changes to the project plan document. In order to
effectively track all of the changes, the project manager should mandate:
A. using an issues log
B. a review of all documents by the change control board
C. version control
D. creating quality metrics
Correct Answer: C
Free VCE & PDF File for CompTIA PK0-003 Real Exam
Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …
100-105 Dumps VCE PDF
200-105 Dumps VCE PDF
300-101 Dumps VCE PDF
300-115 Dumps VCE PDF
300-135 Dumps VCE PDF
300-320 Dumps VCE PDF
400-101 Dumps VCE PDF
640-911 Dumps VCE PDF
640-916 Dumps VCE PDF
70-410 Dumps VCE PDF
70-411 Dumps VCE PDF
70-412 Dumps VCE PDF
70-413 Dumps VCE PDF
70-414 Dumps VCE PDF
70-417 Dumps VCE PDF
70-461 Dumps VCE PDF
70-462 Dumps VCE PDF
70-463 Dumps VCE PDF
70-464 Dumps VCE PDF
70-465 Dumps VCE PDF
70-480 Dumps VCE PDF
70-483 Dumps VCE PDF
70-486 Dumps VCE PDF
70-487 Dumps VCE PDF
220-901 Dumps VCE PDF
220-902 Dumps VCE PDF
N10-006 Dumps VCE PDF
SY0-401 Dumps VCE PDF