[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 291-300

Ensurepass

QUESTION 291

A project manager has been asked to create an issues log. Which of the following should be

included in the issues log? (Select TWO).

 

A.     The description of the issue

B.     The cost of the issue

C.     The risk log

D.     The date the issue was submitted

E.      The work breakdown structure (WBS)

 

Correct Answer: AD

 

 

QUESTION 292

In order to satisfy a difficult stakeholder, a project manager has asked the project team to include

more services than were outlined in the statement of work (SOW). Which of the following will be

the MOST likely impact on the outcome of the project?

 

A.     It may decrease the scope of the project.

B.     It may satisfy the project sponsor.

C.     It may increase the cost of the project.

D.     It may require the use of fewer resources.

 

Correct Answer: C

 

 

 

QUESTION 293

The team members have notified the project manager of several risks which may have a

significant impact upon the project. Which of the following should the project manager do FIRST

to address these risks?

 

A.     Manage the risks with the lowest impact.

B.     Recommend the cancellation of the project.

C.     < span lang="EN-US">Ignore the risks.

D.     Manage the risks with the highest impact.

 

Correct Answer: D

 

 

QUESTION 294

A team member reports that a coworker is difficult and does not follow assigned tasks. Because

the project manager needs to cut project costs, the team member who reported the issue is

terminated. Which of the following conflict resolution techniques is the project manager using?

 

A.     Avoidance

B.     Forcing

C.     Acceptance

D.     Transference

 

Correct Answer: A

 

 

QUESTION 295

Several project tasks cannot be completed because local resources are not available. The project

manager has to outsource the work to find qualified resources. Which of the following risk

responses is the project manager using?

 

A.     Acceptance

B.     Mitigation

C.     Transference

D.     Avoidance

 

Correct Answer: C

 

 

QUESTION 296

A purpose of formal project closure is to:

 

A.     assess blame for the failure of the project

B.     provide lessons learned for future projects

C.     start a new project

D.     outline the responsibilities of each team member

 

Correct Answer: B

 

 

QUESTION 297

A statement of work (SOW) has been heavily revised by the stakeholders. Which of the following

should be implemented to make it easier to determine how many times the document has been

revised?

 

A.     Version control

B.     A document revision date

C.     Approval signatures from each stakeholder

D.     A change request

 

Correct Answer: A

 

 

QUESTION 298

The quality of the finished product does not match stakeholder specifications. Which of the

following steps should a project manager have taken to ensure the quality of the project

deliverable?

 

A.     The project manager should have asked for more project resources.

B.     The project manager should have eliminated the need for change requests.

C.     The project manager should have included details in the WBS dictionary.

D.     The project manager should have monitored the work performance.

 

Correct Answer: D

 

 

QUESTION 299

During which of the following processes in the project lifecycle is risk to the project at its

HIGHEST?

 

A.     Monitoring/Controlling

B.     Planning

C.     Initiation

D.     Execution

 

Correct Answer: C

 

 

QUESTION 300

Which of the following components would be important in creating a project charter?

 

A.     Work Breakdown Structure (WBS)

B.     Portfolio manager

C.     Communications strategy

D.     Business need

 

Correct Answer: D

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , . Bookmark the permalink.