[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 31-40

Ensurepass

QUESTION 31

A company has 50 percent of a project complete. The project plan states:

 

Ÿ   The project will last 10 months

Ÿ   The company will create 150 gadgets per month

Ÿ   The cost to make each gadget will be $55

Ÿ   The total budget is $9,000

 

Which of the following is the planned value for the project?

 

A.     $1,500

B.     $4,500

C.     $8,250

D.     $9,000

 

Correct Answer: B

 

 

 

 

QUESTION 32

Which of the following is included in the project charter?

 

A.     A work performance report

B.     A cost assessment

C.     A high level plan

D.     A risk assessment

 

Correct Answer: C

 

 

QUESTION 33

Which of the following activities occur in the planning phase of a project? (Select TWO).

 

A.     Obtain product acceptance.

B.     Identify the Executive Sponsor.

C.     Assign and explain tasks.

D.     Perform project kick off.

E.      Prepare a project charter.

 

Correct Answer: CD

 

 

QUESTION 34

Transition plans include which of the following elements?

 

A.     Work Breakdown Structure (WBS)

B.     Project warranty

C.     Project process reports

D.   
 
Earned value calculations

 

Correct Answer: B

 

 

QUESTION 35

Which of the following tools can be used to determine if a project deliverable is out of

specification?

 

A.     PERT

B.     RACI chart

C.     Gantt chart

D.     Control chart

 

Correct Answer: D

QUESTION 36

Click on the Exhibit button. Which of the following is the critical path of the network diagram?

 

clip_image002

 

A.     Start-D-E-Finish

B.     Start-C-E-Finish

C.     Start-D-E-F-Finish

D.     Start-B-F-Finish

 

Correct Answer: B

 

 

QUESTION 37

During monitoring/controlling, a defect is found in the project deliverable. In which of the

following processes did this occur?

 

A.     Quality control

B.     Risk assessment

C.     Quality assurance

D.     Stakeholder analysis

 

Correct Answer: A

 

 

QUESTION 38

A project manager needs to determine the trends a process is exhibiting over time. Which of the following tools should the project manager use?

 

A.     Histogram

B.     Ishikawa diagram

C.     Pareto chart

D.     Run chart

 

Correct Answer: D

 

 

QUESTION 39

A project manager conducted a risk probability and impact assessment with the project team. In which of the following risk management processes did this occur?

 

A.     Qualitative risk analysis

B.     Quantitative risk analysis

C.     Risk response planning

D.     Risk identification

 

Correct Answer: A

 

 

QUESTION 40

One of the team members assigned to a project is not performing well. The team member is new and is not experienced in the type of work involved with this project. Which of the following is the BEST response to this situation?

 

A.     Ask other team members to help.

B.     Assign the team member to another project.

C.     Talk to the team member to encourage better performance.

D.     Arrange for training for the team member.

< font face="Calibri"> 

Correct Answer: D

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , . Bookmark the permalink.