[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 331-340

Ensurepass

QUESTION 331

A project manager’s experience shows that when using four laborers they can produce ten

deliverables. Now the project manager uses eight laborers and produces fifteen deliverables.

This is an example of which of the following?

 

A.     Learning curve

B.     Law of diminishing return

C.     80/20 rule

D.     Parametric cost estimating

 

Correct Answer: B

 

 

QUESTION 332

The process of decomposing deliverables into smaller components is complete when:

 

A.     manageable cost and duration estimates can be developed

B.     project justification has been established

C.     change requests have been approved

D.     each work element is found in the WBS and the WBS dictionary

 

Correct Answer: A

 

 

QUESTION 333

A project manager has an initial problem with a remote team member’s performance. Which of

the following is the BEST form of communication to address this issue?

 

A.     Formal written communications

B.     Informal written communications

C.     Informal verbal communications

D.     Formal verbal communications

 

Correct Answer: C

 

 

QUESTION 334

Which of the following techniques graphically represents schedule activities as nodes and uses

arrows to define the sequence relationship between them?

 

A.     Activity-on-Arrow (AOA)

B.     Arrow Diagram Method (ADM)

C.     Work Breakdown Structure (WBS)

D.     Precedence Diagram Method (PDM)

Correct Answer: D

 

 

QUESTION 335

The testing of a deliverable to determine whether or not it meets previously defined acceptance

criteria is an example of which of the following?

 

A.     Quality assurance

B. &nbsp
;  
Change control

C.     Quality control

D.     Risk matrix analysis

 

Correct Answer: C

 

 

QUESTION 336

The design of standards and specifications by which to test the functionality of a deliverable is a

component of which of the following?

 

A.     Scope control

B.     Change control

C.     Quality assurance

D.     Risk matrix analysis

 

Correct Answer: C

 

 

QUESTION 337

Industry regulations require that an organization keep all project-related documents for no less

than seven years. Which of the following should the project manager implement to BEST address

this requirement?

 

A.     Version control policy

B.     Document retention policy

C.     Auditing policy

D.     Standards compliance

 

Correct Answer: B

 

 

 

 

 

 

QUESTION 338

All of the following are included in the project scope document EXCEPT the:

 

A.     project assumptions

B.     key performance indicators

C.     alignment to strategic goals

D.     project charter

 

Correct Answer: D

 

 

QUESTION 339

All of the following are characteristics of a WBS EXCEPT: (Select TWO).

 

A.     shows a graphical timeline of project activities

B.     shows a hierarchal breakdown of project work

C.     shows major project milestones

D.    
used as a tool to make project cost estimates

E.      includes a dictionary as a supporting document

 

Correct Answer: AC

 

 

QUESTION 340

All of the following occur during the project closure phase EXCEPT:

 

A.     ensure the project is aligned with organizational goals

B.     ensure document retention compliance is being performed

C.     release project team resources

D.     close contracts and pay vendors

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.