QUESTION 391

Which of the following occurs during a project kick-off meeting? (Select Two).

 

A.     Work performance information is established.

B.     Risk analysis is performed.

C.     Quality metrics are defined.

D.     Project goals are communicated.

E.      Roles and responsibilities of the project team are identified.

 

Correct Answer: DE

 

 

QUESTION 392

A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:

 

A.     internal process compliance

B.     risk avoidance

C.     standards compliance

D.     audit trail compliance

 

Correct Answer: C

 

 

QUESTION 393

Which of the following should be created in the project closing documentation? (Select Two).

 

A.     Closure report summarizing costs

B.     Responsibility assessment matrix

C.     Lessons learned

D.     Project timeline

E.      Statement of Work (SOW)

 

Correct Answer: AC

 

 

 

 

QUESTION 394

A project can be defined as which of the following?

 

A.     A high level cost estimate.

B.     An ongoing work assignment.

C.     A temporary endeavor with unlimited time or cost for completion.

D.     A temporary endeavor limited by time or cost.

 

Correct Answer: D

 

 

QUESTION 395

Which of the following elements would be needed to prepare an effective project scope

document?

 

A.     An approved project milestone schedule

B.     An approved risk assessment document

C.     An approved project charter

D.     A responsibility assignment matrix

 

Correct Answer: C

 

 

QUESTION 396

In which of the following organization types is it LEAST likely that a conflict regarding competing

demands for resources would take place?

 

A.     Functional

B.     Weak Matrix

C.     Balanced Matrix

D.     Projectized

 

Correct Answer: D

 

 

QUESTION 397

Which of the following elements does a project charter contain?

 

A.     A project scope statement

B.     A change management template

C.     A completed request for proposal (RFP)

D.     A complete list of the key performance indicators (KPIs)

 

Correct Answer: A

QUESTION 398

Which of the following describes the point in time when resources can be assigned to scheduled

tasks?

 

A.     When the project statement of work (SOW) has been created.

B.     When the project deliverables have been defined.

C.     When the work breakdown structure (WBS) is decomposed into work packages.

D.     When the project WBS dictionary has been created.

 

Correct Answer: C

 

 

QUESTION 399

During which of the following process groups is the preliminary project risk assessment

performed?

 

A.     Monitoring/Controlling

B.     Planning

C.     Initiating

D.     Executing

 

Correct Answer: B

 

 

QUESTION 400

Which of the following is a use for a Pareto diagram?

 

A.     In procurement management to evaluate vendor proposals.

B.     In cost management to determine actual versus expected project costs.

C.     In quality management to identify and prioritize problem areas.

D.     In risk management to assess potential project risk occurrences.

 

Correct Answer: C

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Exam Questions (December) and tagged , , , , , , . Bookmark the permalink.