[Free] Download New Updated (December) CompTIA PK0-003 Exam Questions 61-70

Ensurepass

QUESTION 61

Which of the following are components of a project charter? (Select THREE).

 

A.     Communication requirements

B.     Risk assessment

C.     Project objectives

D.     Problem statement

E.      Stakeholder identification

F.      Work Breakdown Structure (WBS)

 

Correct Answer: CDE

 

 

QUESTION 62

Which of the following would be included in a project scope document? (Select THREE).

 

A.     Project constraints

B.     Gantt chart

C.     Work Breakdown Structure (WBS)

D.     Project roles and responsibilities

E.      Key Performance Indicators (KPIs)

F.      Detailed project objectives

 

Correct Answer: AEF

 

 

QUESTION 63

Which of the following are common components of a project transition plan? (Select TWO).

 

A.     Extended support

B.     Work performance

C.     Ownership identification

D.     Risk assessment

E.      Budget analysis

 

Correct Answer: AC

 

 

QUESTION 64

The communication plan states the weekly project status updates will be distributed via email.

Which of the following components of a communication plan is missing?

 

A.     Frequency

B.     Format

C.     Distribution list

D.     Method of distribution

 

Correct Answer
: C

QUESTION 65

Which of the following personnel should sign the project charter?

 

A.     A representative from the project management office.

B.     The project manager.

C.     The most senior project team member.

D.     An executive with the power to authorize the project.

 

Correct Answer: D

 

 

QUESTION 66

Which of the following would be included in the project charter? (Select TWO).

 

A.     Project description

B.     Risk management plan

C.     Change management plan

D.     Statement of Work (SOW)

E.      High level business case

 

Correct Answer: AE

 

 

QUESTION 67

An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on the project?

 

A.     Cost will decrease and time will increase.

B.     Cost will decrease and time will decrease.

C.     Cost will increase and time will increase.

D.     Cost will increase and time will decrease.

 

Correct Answer: D

 

 

QUESTION 68

Which of the following describes crashing a project schedule?

 

A.     Project activities that would normally be completed in sequence are performed concurrently.

B.     Additional resources are deployed.

C.     All float time is removed from the project schedule.

D.     The project manager reviews the project scope to determine unnecessary requirements.

 

Correct Answer: B

 

 

QUESTION 69

Which of the following activities occur during a project kick-off meeting? (Select TWO).

 

A.     Ensuring the project meets the organization’s strategic objectives.

B.     Signing the project charter and sta
tement of work.

C.     Selecting the project manager and project sponsor.

D.     Reviewing the project goals and objectives.

E.      Defining the project team roles and responsibilities.

 

Correct Answer: DE

 

 

QUESTION 70

A project manager is performing activity sequencing with the project team. Each activity is

written in a box with arrows linking the boxes according to their dependencies. Which of the

following tools is the project manager utilizing?

 

A.     Arrow Diagramming Method (ADM)

B.     Precedence Diagramming Method (PDM)

C.     Critical Path Method (CPM)

D.     Critical Chain Method (CCM)

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , . Bookmark the permalink.