Ensurepass

QUESTION 91

Which of the following risk response strategies reduces the impact of an event without changing

the project’s objectives?

 

A.     Acceptance

B.     Avoidance

C.     Mitigation

D.     Transfer

 

Correct Answer: C

 

 

QUESTION 92

A Pareto chart is a special type of:

 

A.     histogram

B.     Ishikawa diagram

C.     scatter diagram

D.     run chart

 

Correct Answer: A

 

 

QUESTION 93

Which of the following is the definition of decomposition?

 

A.     Using Ishikawa diagrams to analyze quality issues and determine the root cause of the issues.

B.     Breaking down the project deliverables into easily manageable work packages.

C.     Evaluating project characteristics in a mathematical model to predict total project costs.

D.     Calculating the project’s early start and finish dates and late start and finish dates to

determine the overall project schedule.

 

Correct Answer: B

 

 

QUESTION 94

Which of the following would require that the project risk register be updated?

 

A.     A qualitative risk analysis is performed.

B.     A stakeholder has concerns about material delays.

C.     The risk management plan is created.

D.     Increased costs for required materials.

 

Correct Answer: A

 

 

QUESTION 95

Which of the following would be an output of a qualitative risk analysis?

 

A.     The risk register is updated.

B.     The risk management plan is created.

C.     The risk management plan is updated.

D.     The risk register is created.

 

Correct Answer: A

 

 

QUESTION 96

Which of the following are tools used in quality control? (Select TWO).

 

A.     Gantt chart.

B.     Ishikawa diagram.

C.     Parametric estimating.

D.     Probability and impact matrix.

E.      Pareto chart.

 

Correct Answer: BE

 

 

 

 

QUESTION 97

Which of the following documents are required to create a risk management plan? (Select TWO).

 

A.     Work Breakdown Structure (WBS)

B.     Risk register

C.     Project scope statement

D.     Statement of Work (SOW)

E.      Project management plan

 

Correct Answer: CE

 

 

QUESTION 98

Which of the following are included in a risk register? (Select TWO).

 

A.     Project risk responses

B.     Identified risks

C.     Major milestones

D.     Risk analysis tools

E.      Risk control board members

 

Correct Answer: AB

 

 

QUESTION 99

A project has produced 2000 of the same deliverable. The project manager does not have time to

inspect every deliverable, but would like some assurance the deliverables are meeting the

specifications. Which of the following techniques should be used?

 

A.     Defect repair review

B.     Process analysis

C.     Statistical sampling

D.     Design of experiments

 

Correct Answer: C

 

 

QUESTION 100

The project manager will define a scale of probability from “unlikely” to “certain” in which of the

following documents?

 

A.     Risk management plan

B.     Scope management plan

C.     Quality management plan

D.     Schedule management plan

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in Uncategorized and tagged , , , , . Bookmark the permalink.