QUESTION 111

Although a needed item can be made in-house, it has been determined that it will be procured. Since the scope is well-defined, which of the following procurement documents should be used and which contract type should result?

 

A.

Request for proposal, and cost plus contract

B.

Request for quote, and time and material contract

C.

Request for bid, and fixed price contract

D.

Request for information, and unit price contract

 

Correct Answer: C

 

 

QUESTION 112

Which of the following allows the ability to assess the validity of a project during pivotal points within a schedule?

 

A.

Initial risk assessment

B.

Phase gates

C.

Milestone

D.

Project charter review

 

Correct Answer: B

 

 

QUESTION 113

A project manager has uncovered that the optimal weight of the magnet that the stakeholders approved for the project is wrong. Which of the following BEST illustrates the problem?

 

A.

Pareto chart

B.

Ishikawa diagram

C.

PERT diagram

D.

Gantt chart

 

Correct Answer: B

 

 

QUESTION 114

While doing scheduled network analysis, it has been determined that the project is forecasted to complete two weeks later than the target date. Which of the following could assist in bringing the forecast in line with the stakeholder expectations?

 

A.

Replacing physical meetings with calls

B.

Adjusting the estimates to best case

C.

Minimizing the schedule buffer

D.

Adding resources to the critical path

 

Correct Answer: D

QUESTION 115

Which of the following represents the difference between the planned budget and the final cost to complete the project?

 

A.

ETC

B.

BAC

C.

EAC

D.

VAC

 

Correct Answer: D

 

 

QUESTION 116

The customer has significantly decreased the timeline on an active project. Which of the following is MOST likely to occur if the existing project scope is maintained?

 

A.

Quality will increase and cost will decrease

B.

Quality will decrease and cost will decrease

C.

Quality will decrease and cost will increase

D.

Quality will increase and cost will increase

 

Correct Answer: C

 

 

QUESTION 117

Which of the following roles has decision making authority with regard to modifying the scope of an ongoing project?

 

A.

Change Control Board

B.

Project Sponsor

C.

Project Leadership Team

D.

Project Manager

 

Correct Answer: A

 

 

QUESTION 118

A software development project just went live and the operations team is now using the software. However, the operations team is having a significant number of difficulties operating the software. Which of the following is the MOST likely cause of this situation?

 

A.

Poor transition plan

B.

Poor lessons learned

C.

Poor scope analysis

D.

Poor quality assurance

 

Correct Answer: A

 

 

 

 

 

 

QUESTION 119

While heading into a meeting to discuss the forecast of the project, it is realized that the report does not contain the EAC. The project manager decides to quickly calculate the EAC. The AC is $2,000, the PV is $4,000, the EV is $3,400, and the BAC is $50,000. Which of the following represents the EAC?

 

A.

$29,411.76

B.

$42,372.88

C.

$58,823.53

D.

$84,745.76

 

Correct Answer: A

 

 

QUESTION 120

Which of the following techniques provides the MOST positive outcomes to conflict? (Select THREE).

 

A.

Forcing

B.

Smoothing

C.

Influencing

D.

Negotiating

E.

Avoiding

F.

Convincing

G.

Socializing

H.

Compromising

I.

Confronting

 

Correct Answer: BDH

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: Com
pTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , . Bookmark the permalink.