QUESTION 121

While working on a project, one of the previously recognized threats occurred. In addition to updating the risk register, which of the following documents should be updated?

 

A.

Communication plan

B.

WBS

C.

Issue log

D.

Project schedule

 

Correct Answer: C

 

 

QUESTION 122

A key stakeholder calls the project manager and asks to
include an enhancement to the product which should be simple to implement. If the project manager agrees to this enhancement, which of the following components of the project plan will be MOST impacted?

 

A.

Scope

B.

Risk

C.

Quality

D.

Resource

 

Correct Answer: A

 

 

QUESTION 123

The project manager has been given the choice to hire five new employees for EVM analysis or subcontract the EVM work to a small business. This choice is referred to as a:

 

A.

gap analysis.

B.

needs assessment.

C.

vendor selection.

D.

make verses buy decision.

 

Correct Answer: D

 

 

QUESTION 124

Which of the following is the main purpose of a work breakdown structure?

 

A.

To decompose the list of deliverables

B.

To identify key stakeholders and their influence

C.

To assign resources to activities

D.

To determine total project duration

 

Correct Answer: A

 

 

QUESTION 125

Which of the following is the primary purpose of a WBS?

 

A.

Decomposition of tasks in a project

B.

Description of basic components of a project

C.

Determination of impacting risks

D.

Identification of basic budgetary requirements

 

Correct Answer: A

 

 

QUESTION 126

Which of the following are objectives of the project kick-off meeting and common activities performed during this meeting? (Select FOUR).

 

A.

Describe the work breakdown structure

B.

Present the roles and responsibilities

C.

Describe the project goals and objectives

D.

Present a high level project timeline

E.

Communicate stakeholder expectations

F.

Present the management plan

G.

Present the communication plan

H.

Communicate the detailed budget

 

Correct Answer: BCDE

 

 

QUESTION 127

Given the following activity:

 

Provide details of errors within the software that occur during verification testing that provide enough evidence that allows the software developers to resolve the errors.

 

Which of the following components is this known as within the quality management plan?

 

A.

Quality control

B.

Quality metrics

C.

Quality baseline

D.

Quality assurance

 

Correct Answer: A

 

 

QUESTION 128

The change control board has approved changes. Which of the following MOST likely reflects the impact of the approved changes on the triple constraints?

 

A.

Changes do not affect the triple constraints.

B.

Variance would occur, as change is a deviation from the baselines.

C.

Revised baselines are established.

D.

Cost and schedule variance are reset to zero.

 

Correct Answer: C

 

 

QUESTION 129

A project has lost critical project team members. Which of the following scheduling methods would be used to analyze the impact of this resource constraint?

 

A.

CCM

B.

PDM

C.

ADM

D.

CCB

 

Correct Answer: A

 

 

QUESTION 130

A change has been approved to move the weekly status meetings from Friday to Tuesday. In addition to notating the change decision in the change log, which of the following documents should be updated?

 

A.

Project plan

B.

Communication plan

C.

Human resource plan

D.

Schedule baseline

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , , , . Bookmark the permalink.