QUESTION 141

A defect in an application code is observed and documented in the middle of a project. The defect is noted as a security risk and requires immediate action. Who is responsible for approving the required fix?

 

A.

Contracting officer

B.

Lead developer

C.

Change control board

D.

Risk management team

 

Correct Answer: C

 

 

QUESTION 142

Which of the following are valid conflict resolution techniques?

 

A.

Smoothing, forcing, compromising, avoiding, and influencing

B.

Smoothing, forcing, considering, avoiding, and negotiating

C.

Smoothing, enforcing, compromising, avoiding, and negotiating

D.

Smoothing, forcing, compromising, avoiding, and negotiating

 

Correct Answer: D

 

 

QUESTION 143

While creating a project schedule, multiple inputs were considered during estimating, allowing for the identification of best case, worst case, and expected case. Which of the following types of schedule methods will reflect this?

 

A.

PERT

B.

CPM

C.

CCM

D.

GERT

 

Correct Answer: A

 

 

 

 

 

 

QUESTION 144

A project manager
is working to select a hosting provider prior to the launch of a new web- based application. To reduce the impact of downtime due to catastrophic natural events, the project manager selects a provider with geographically diverse datacenters. This is an example of which of the following risk response strategies?

 

A.

Acceptance

B.

Avoidance

C.

Mitigation

D.

Transfer

 

Correct Answer: C

 

 

QUESTION 145

Which of the following would be the MOST important inputs for the development of a project schedule? (Select TWO).

 

A.

Activity durations

B.

Procurement plan

C.

Project assumptions

D.

Task dependencies

E.

Cost estimates

 

Correct Answer: AD

 

 

QUESTION 146

A project activity has a schedule that allows a late start on day 10 and a late finish on day 20. The project manager has determined an early start could occur on day 7 with an early finish
on day 14. Which of the following does this schedule identify?

 

A.

A lead

B.

A buffer

C.

A float

D.

A lag

 

Correct Answer: C

 

 

QUESTION 147

In which of the following should a project manager maintain a list of identified risks?

 

A.

Risk register

B.

Risk assessment

C.

Risk management plan

D.

Risk tolerance

 

Correct Answer: A

 

 

 

 

QUESTION 148

Which of the following is a cost estimation technique that uses historical data?

 

< p class="MsoNormal" style="margin: 0cm 0cm 0pt; line-height: normal; text-autospace: ; mso-layout-grid-align: none" align="left">A.

Expert judgment

B.

Parametric estimating

C.

Reserve analysis estimating

D.

Group decision-making techniques

 

Correct Answer: B

 

 

QUESTION 149

Which of the following cost estimating techniques relies on the actual costs of previously completed projects that are similar in nature?

 

A.

Bottom-up

B.

Three-point

C.

Analogous

D.

Parametric

 

Correct Answer: C

 

 

QUESTION 150

A project manager just completed a project closure. The project manager completed the following activities: Verify all objectives were completed, all resources were released and all contracts were closed. Which of the following other project closure related activities are missing?

 

A.

Lessons learned, customer signoff, update organizational documents and update historical information

B.

Lessons learned, customer signoff, schedule closure and update historical information

C.

Project manager signoff, customer signoff, update organizational documents and update historical information

D.

Lessons learned, budget signoff, update organizational documents and update financial information

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …