QUESTION 191

Which of the following includes verifying that the project scope was satisfied and lessons learned are updated once the product has been accepted by the customer?

 

A.

Fast tracking

B.

Risk retirement

C.

Project closure

D.

Post mortem analysis

 

Correct Answer: C

 

 

QUESTION 192

Which of the following is the status of an active
project with an SPI of 1.1 and a CPI of .9?

 

A.

Behind schedule, and over budget

B.

Ahead of schedule, and under budget

C.

Behind schedule, and under budget

D.

Ahead of schedule, and over budget

 

Correct Answer: D

 

 

QUESTION 193

A project consists of completing a technical refresh of a datacenter. The existing network infrastructure does not support the new network cards. A conflict arises with the technical refresh schedule because it now depends on an upgrade to the network infrastructure. The network infrastructure team did not plan and does not have the budget to upgrade until two years from now. The project manager talks to the stakeholders to explain that the project cannot continue until the network infrastructure is upgraded. The stakeholders agree to pay for the network infrastructure upgrade and to allow the schedule to slip. Which of the following conflict resolution techniques does this scenario describe?

 

A.

Forcing

B.

Negotiating

C.

Smoothing

D.

Avoiding

 

Correct Answer: A

 

 

QUESTION 194

In a project manager’s status report, it shows an earned value of $40,000 and actual costs of $39,000 with a planned value of $55,000. Which of the following is the Cost Performance Index (CPI) of this project and is it ahead or behind schedule?

 

A.

CPI = 1.38, ahead of schedule

B.

CPI = 0.72, behind schedule

C.

CPI = 1.03, behind schedule

D.

CPI = 0.98, ahead of schedule

 

Correct Answer: C

 

 

QUESTION 195

A project involves outsourcing multiple parts of the software application to developers around the world. Which of the following is MOST likely to impact meeting attendance?

 

A.

Time zone differences

B.

Cultural differences

C.

Language barriers

D.

Technology barriers

 

Correct Answer: A

 

 

QUESTION 196

Which of the following are parts of decision oversight? (Select TWO).

 

A.

Change control board

B.

Committee consulting

C.

Tollgate approval

D.

Audit trails

E.

Local laws

 

Correct Answer: AB

 

 

QUESTION 197

Which of the following is contained in the WBS dictionary?

 

A.

Responsibility matrix

B.

Key performance indicators

C.

Account identifiers

D.

Project stakeholders

 

Correct Answer: C

 

 

QUESTION 198

Which of the following tools should be used to analyze quality issues? (Select TWO).

 

A.

Risk register

B.

Pareto chart

C.

Histogram

D.

SWOT analysis

E.

RACI chart

 

Correct Answer: BC

 

 

QUESTION 199

A change to the project has been requested by a key stakeholder. Which of the following will the project manager do FIRST?

 

A.

Inform the team of the change

B.

Implement the change

C.

Approve the change

D.

Review the change

 

Correct Answer: D

 

 

QUESTION 200

A project manager is in the process of developing a charter. The project manager is concerned about communicating with affected business groups. Which of the following needs to be done to ensure all necessary parties are engaged in the effort?

 

A.

Reviewing the work breakdown structure

B.

Identifying the stakeholders

C.

Developing the project baseline

D.

Drafting the change management plan

 

Correct Answer: B

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , . Bookmark the permalink.