QUESTION 21

It is the first week after a project kick-off. The project team is not making much progress on decisions needed and are disagreeing with each other. Which of the following represents the team’s current stage?

 

A.

Storming

B.

Norming

C.

Forming

D.

Performing

 

Correct Answer: A

 

 

QUESTION 22

The project team members have determi
ned they need to procure hardware before they will be able to create a product to test. This activity sequencing was created using which of the following types of dependency?

 

A.

Mandatory

B.

External

C.

Discretionary

D.

Internal

 

Correct Answer: A

 

 

QUESTION 23

A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue until the hardware is replaced. This repair will put the project behind schedule by a week. Which of the following actions should the project manager do FIRST?

 

A.

Prepare performance report

B.

Manage the issue

C.

Schedule a meeting

D.

Update communication plan

 

Correct Answer: B

 

 

QUESTION 24

A project is experiencing quality issues with the deliverable product. Which of the following tools would be used to identify and prioritize the MOST commonly occurring issues?

 

A.

Scatter diagram

B.

Pareto chart

C.

Ishikawa diagram

D.

Trend analysis

 

Correct Answer: B

 

 

QUESTION 25

A project team has to implement a key part of their solution from an external vendor. After sending out an RFP, the team has narrowed the possible providers down to three. Which of the following should the project manager do NEXT?

 

A.

Hold a steering committee meeting to discuss the options

B.

Ask the project team to take a vote on the vendor

C.

Begin contract negotiations with the lowest offer

D.

Contact project stakeholders individually and discuss the RFP

 

Correct Answer: A

 

 

QUESTION 26

When performing quantitative risk analysis, which of the following should be produced?

 

A.

Control chart

B.

Decision tree

C.

Run chart

D.

Scatter diagram

 

Correct Answer: B

 

 

QUESTION 27

Which of the following would be found in a post-mortem analysis? (Select TWO).

 

A.

Lessons Learned

B.

Transition Plan

C.

Project sponsor signoff

D.

Maintenance responsibilities

E.

Reasons for early termination of the project

 

Correct Answer: AE

 

 

QUESTION 28

In a project kick-off meeting, the project manager does which of the following?

 

A.

Discusses pending change requests

B.

Obtains approval on the budget

C.

Receives buy in from the stakeholders

D.

Reviews the project goals

 

Correct Answer: D

 

 

QUESTION 29

A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?

 

A.

Change request

B.

Risk

C.

Resource constraint

D.

Scope creep

 

Correct Answer: D

 

 

QUESTION 30

A project manager has found that the project is running behind schedule. After considering the alternatives, is it possible to both fast track and crash a project?

 

A.

Yes, they are not mutually exclusive.

B.

No, it is too risky to do both at the same time.

C.

Only if they crash the project before they fast track it.

D.

Yes, fast tracking and crashing are the same activity.

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , , , . Bookmark the permalink.