QUESTION 61

A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change’s effect on the project?

 

A.

Performing an impact analysis

B.

Identifying a change

C.

Coordinating with stakeholders to select the course of action

D.

Filling out a change control

 

Correct Answer: A

 

 

QUESTION 62

A project manager will initially baseline a project when:

 

A.

change requests are approved.

B.

stakeholders request project initiation.

C.

creating a project charter.

D.

tasks and estimates have been identified.

 

Correct Answer: D

 

 

QUESTION 63

The project manager wants to report to the stakeholders to date project’s cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following is the cost variance?

 

A.

-5%

B.

5%

C.

-$10,000

D.

$10,000

 

Correct Answer: C

 

 

QUESTION 64

A project manager was informed that a task will be delayed by four weeks. To determine the impact on the overall project, which of the following will the project manager need to update FIRST?

 

A.

WBS

B.

Risk log

C.

Project schedule

D.

Scope statement

 

Correct Answer: C

QUESTION 65

An email to end users regarding the go-live of an upcoming software release is an example of:

 

A.

interactive method.

B.

push method.

C.

formal method.

D.

pull method.

 

Correct Answer: B

 

 

QUESTION 66

Please refer to the attached graphic and review the following task description. Which of the following is the project schedule critical path?

 

clip_image002

 

A.

A,E,F,B,G,H,D

B.

A,E,F,B,H,D

C.

A,G,H,D

D.

A,E,F,C,D

 

Correct Answer: A

 

 

QUESTION 67

Which of the following are the characteristics of a project? (Select TWO).

 

A.

Contains a procurement plan

B.

Utilizes a chart of accounts

C.

Requires resource leveling

D.

Definitive beginning and end

E.

Produces a deliverable

 

Correct Answer: DE

 

 

QUESTION 68

Which of the following inputs are used in quality control? (Select TWO).

 

A.

Quality metrics

B.

Quality reviews

C.

Quality checklists

D.

Quality corrective actions

E.

Quality change request

 

Correct Answer: AC

 

 

QUESTION 69

Given the following:

 

1. Senior management support will maintain throughout the duration of the project.

 

2. Technical hardware onsite is sufficient to support the new application.

 

3. Network connectivity is able to support the new product.

 

4. All scope changes will follow the change control process.

 

Which of the following components of a scope document would BEST capture the above criteria?

 

A.

Assumptions

B.

Constraints

C.

Key performance indicators

D.

Objectives

 

Correct Answer: A

 

 

QUESTION 70

Two project resources have been involved in several heated arguments based on approaches to meet project requirements. The first resource is convinced that the requirement is invalid, whereas the second resource believes that the requirement is valid but should be solved a certain way. As a project manager, which of the following is a suitable conflict resolution approach to attempt to remedy the situation?

 

A.

Attempt `smoothing’ and `negotiation’ techniques

B.

Threaten to report both employees to HR due to bullying

C.

Make an executive decision as the project manager

D.

Escalate the matter to the project sponsor

 

Correct Answer: A

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , , , . Bookmark the permalink.