QUESTION 81

Which of the following would use the WBS to aid in the creation of the cost estimate?

 

A.

Analogous

B.

Top down

C.

Parametric

D.

Bottom up

 

Correct Answer: D

 

 

QUESTION 82

When a project manager is leading the team through the norming stage of team growth, the project team:

 

A.

is performing in a highly efficient manner.

B.

has reached full capacity.

C.

is seeing a decrease in productivity.

D.

is working together and comfortable.

 

Correct Answer: D

 

 

QUESTION 83

A third party product warranty is an example of which of the following types of risk response?

 

A.

Risk sharing

B.

Risk avoidance

C.

Risk acceptance

D.

Risk transfer

 

Correct Answer: D

 

 

QUESTION 84

A well-written scope document will include which of the following? (Select TWO).

 

A.

Contact information

B.

Milestones

C.

Stakeholders

D.

Constraints

E.

Project acceptance criteria

F.

Project tasks

 

Correct Answer: DE

 

 

 

 

 

QUESTION 85

A project manager schedules a weekly meeting to review the project schedule. The project manager is looking for an easy way to see the project tasks and review areas where tasks may overlap and are dependent on others. Which of the following would provide the project manager with the BEST project view?

 

A.

PERT

B.

Pareto

C.

CPM

D.

Gantt

 

Correct Answer: D

 

 

QUESTION 86

The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies?

 

A.

Transferring

B.

Enhancing

C.

Sharing

D.

Exploiting

 

Correct Answer: C

 

 

QUESTION 87

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure. This type of analysis is an example of which of the following?

 

A.

Cost performance index

B.

Risk mitigation

C.

Schedule variance

D.

Cost variance

 

Correct Answer: C

 

 

QUESTION 88

A project has been running for four months. The planned value to this point is $100,000. The actual cost is an average of $30,000 per month. Earned value is $90,000. Which of the following is the current cost performance index?

 

A.

0.75

B.

1.25

C.

$20,000 over budget

D.

Not enough detail to determine

 

Correct Answer: A

QUESTION 89

Which of the following communication methods would be used to update the project steering committee?

 

A.

Daily phone conferences outlining key activities

B.

A monthly financial and project summary report

C.

A daily email highlighting the project spend

D.

A standup meeting with the entire project team

 

Correct Answer: B

 

 

QUESTION 90

A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?

 

A.

SPI = 0.89, ahead of schedule

B.

SPI = 0.90, behind schedule

C.

SPI = 1.11, behind schedule

D.

SPI = 1.20, ahead of schedule

 

Correct Answer: D

 

Free VCE & PDF File for CompTIA PK0-003 Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in PK0-003 Actual Test (October 2016) and tagged , , , , , . Bookmark the permalink.