QUESTION 1  (Topic 1)

 

clip_image001

 

This is an example of part of a:

 

A.

QFD Matrix

B.

Activity Network Diagram

C.

Interr
elationship Diagram

D.

Affinity Diagram

 

Answer: A

 

 

QUESTION 2  (Topic 1)

 

A team wants a technique for improving consistency of assembly operations. They should

 

 

 

 

use:

 

A.

written and diagrammed work instructions

B.

flow charts and process maps

C.

cause and effect diagrams

D.

Pareto chart

E.

relationship matrix

 

Answer: A

 

 

QUESTION 3  (Topic 1)

 

A team is investigating ways to reduce power outages. They determine that an outage can occur in only three ways: grid failure, local transformer failure or local overload. They then investigate each of these three events for possible causes, etc. They draw a diagram that “fans out” using the power outage as the handle of the fan. These improvements are best described by which approach to problem solving?

 

A.

Affinity diagram

B.

Inter-relationship digraph

C.

Tree diagram

D.

Process decision program chart

E.

Matrix diagram

F.

Prioritization matrix

 

F.Activity network diagram

 

Answer: C

 

 

QUESTION 4  (Topic 1)

 

The team in the above problem draws arrows from Post-It?notes that are causes to notes that are the effects of these causes. This step is best described by which approach to problem solving?

 

A.

Affinity diagram

B.

Inter-relationship digraph

C.

Tree diagram

D.

Process decision program chart

E.

Matrix diagram

F.

Prioritization matrix

 

 

 

 

G.

Activity network diagram

 

Answer: B

 

 

QUESTION 5  (Topic 1)

 

The quality leader most associated with the concept of robustness:

 

A.

Juran

B.

Ishikawa

C.

Crosby

D.

Feigenbaum

E.

Taguchi

F.

none of the above

 

Answer: E

 

 

QUESTION 6  (Topic 1)

 

This table displays the inventory of fasteners in a storage cabinet. An item is selected at random from the fastener cabinet. Find the approximate probability it is a bolt.

 

clip_image002

 

 

 

 

 

A.

160

B.

.160

C.

.09

D.

.30

E.

none of the above

 

Answer: D

 

 

QUESTION 7  (Topic 1)

 

The following data were collected on the diameters of turned shafts: 2.506 2.508 2.505

Q1

505. These values are:

I.Attribute data II. Discrete data III. Variables data IV. Continuous data

 

A.

I and II A stable, normally distributed process with specification 3.50 .03 has = = .016.

What percent of the production violates specification?

B.

I only

C.

II only

D.

I and IV

E.

III and IV

 

Answer: E

 

 

QUESTION 8  (Topic 1)

 

(Refer to the previous problem) To estimate the within treatment variance the experimenters would calculate the variances of:

 

A.

all 80 readings

B.

the five replications for each run

C.

the runs for which a factor is at its lowest level

 

Answer: B

 

 

QUESTION 9  (Topic 1)

 

Find the value of (9) in the ANOVA table. Assume:

 

 

 

 

 

clip_image003

 

A.

16.4

B.

3.2

C.

18.6

D.

23.2

E.

4.54

F.

12.2

G.

0.525

H.

2.82

I.

1.48

J.

35.4

K.

0.10<P<1

L.

0.05<P<0.10

M.

0.01<P<0.05

N.

0.005<P<0.01

O.

0<P<0.005

 

Answer: F

 

 

QUESTION 10  (Topic 1)

 

SWOT is an acronym for:

 

A.

strengths, weaknesses, opportunities, threats

B.

statistics without tables

C.

sensory Weibull ordinal tools

D.

success wields optimal teams

E.

< font face="Arial">none of the above

 

Answer: A

Free VCE & PDF File for ASQ CSSBB Real Exam

Instant Access to Free VCE Files: CompTIA | VMware | SAP …
Instant Access to Free PDF Files: CompTIA | VMware | SAP …

This entry was posted in CSSBB Real Exam (October) and tagged , , , , , , . Bookmark the permalink.